THE EVIDENCE

What independent research shows about retro-commissioning

EBEWE requires an audit and retro-commissioning every five years. National lab studies show this work often pays for itself. Results vary by building, so we screen for exemptions first and never promise savings.

EBEWE applies to covered buildings; exemptions may apply. Read the City requirements

Published studies

Showing 7 of 7 studies

  • Large studies

    16% median savings, ~1-year payback

    Berkeley Lab study of 643 U.S. buildings

    This California Energy Commission-sponsored analysis covered 643 U.S. buildings, including existing and new construction. Existing-building commissioning delivered median whole-building energy savings of 16% with a 1.1-year payback; offices showed about 9% median energy-cost savings, a different measure.

    Source: Lawrence Berkeley National Laboratory, 2009Read the source for Berkeley Lab study of 643 U.S. buildings
  • Large studies

    15% savings, 0.7-year payback

    U.S. DOE summary

    DOE’s existing-building commissioning guide summarizes an analysis with median whole-building energy savings of 15% and a 0.7-year payback. Median commissioning costs in that historical sample were approximately $0.27 per square foot—not a current ECCP price.

    Source: U.S. Department of EnergyRead the source for U.S. DOE summary
  • Office & commercial

    12.1% average savings

    26 federal offices and courthouses

    PNNL reviewed re-tuning in 26 federal offices and courthouses whose starting performance was already efficient. Adjusting building controls still produced average annual energy savings of 12.1% across that group.

    Source: Pacific Northwest National Laboratory, 2017Read the source for 26 federal offices and courthouses
  • Office & commercial

    12% median savings

    20 office buildings

    PNNL identified re-tuning opportunities in 20 office buildings, and operating teams implemented many of the suggested measures. Preliminary results for buildings implementing measures ranged from 2–21% energy savings, with a 12% median.

    Source: PNNL / Penn State CBEI (Archived original source; preliminary results.)Read the source for 20 office buildings
  • Office & commercial

    34.7% electricity savings

    Georgia Tech research building

    This complex research building illustrates the upper end of what controls corrections can achieve. Its case study reports 34.7% electricity savings over two years compared with projected usage, not a typical whole-building energy result.

  • Apartments

    ~50% base energy savings

    Sunset Towers, multifamily

    Recommissioning the central plant at Sunset Towers made better use of existing equipment with limited new investment. The project account reports approximately 50% savings in base energy use, primarily domestic hot water—not a 50% reduction in all building energy.

    Source: Impact Engineering via Passive House AcceleratorRead the source for Sunset Towers, multifamily
  • Apartments

    Up to 14% cost savings

    Hot water recirculation controls

    DOE-funded testing compared hot water recirculation controls in two New York apartment buildings. Accounting for interactions with space heating and cooling, estimated annual cost savings ranged from 1–14%, depending on the control method.

Results vary by building.

Retro-commissioning does not always produce energy savings, and results depend on the building and the systems being tuned. That’s why we check exemptions first and give estimates by building type, never guarantees.

ACEEE: Retrocommissioning and Building Tune-Up Policies

Want an estimate for your building?